ULDC contractor extension, hospital revenue certificate reissuance, LAS generator, Juvenile Justice grant, Val Del Estates infrastructure @ LCC Packet 2023-10-23 [Up]

LAKE blog posts:

Documents received in response to a LAKE open records request:

Pictures

M

[Collage @ LCC Packet 2023-10-23]
Collage @ LCC Packet 2023-10-23

October-23-24-2023-Meeting-Packet

[PROPOSED AGENDA]
PROPOSED AGENDA
PDF

Extension of Agreement for ULDC Updates with Goodwyn Mills Cawood

[BUDGET IMPACT: Not to exceed $15,000.00]
BUDGET IMPACT: Not to exceed $15,000.00
PDF

Acceptance of FY2024 Juvenile Justice Delinquency Prevention Grant

[BUDGET IMPACT: $50,000.00 - fully funded through reimbursement by CJCC FUNDING]
BUDGET IMPACT: $50,000.00 - fully funded through reimbursement by CJCC FUNDING
PDF

Adopt Resolution Accepting Infrastructure for Val Del Estates Subdivision Phase IV

[BUDGET IMPACT: N/A includes 22 residential lots. Engineering and Utilities staff have made the final inspection of the construction of Phase IV,]
BUDGET IMPACT: N/A includes 22 residential lots. Engineering and Utilities staff have made the final inspection of the construction of Phase IV,
PDF

Land Application System (LAS) Generator

[BUDGET IMPACT: $48,068.00 to run the aerators in the treatment ponds. The generator there now is not sized to handle this and will be relocated to the Val Tech lift station.]
BUDGET IMPACT: $48,068.00 to run the aerators in the treatment ponds. The generator there now is not sized to handle this and will be relocated to the Val Tech lift station.
PDF

Reissuance of Hospital Authority Refunding Revenue Anticipation Certificates

[The Authority is now planning to lease the hospital facilities financed or refinanced by the 2019 Certificates to a new corporation named South Georgia Medical Center, Inc.]
The Authority is now planning to lease the hospital facilities financed or refinanced by the 2019 Certificates to a new corporation named South Georgia Medical Center, Inc.
PDF

[A RESOLUTION AUTHORIZING AND APPROVING THE REISSUANCE BY THE]
A RESOLUTION AUTHORIZING AND APPROVING THE REISSUANCE BY THE
PDF

[Section 1. The Board of Commissioners hereby approves and authorizes the Chairman]
Section 1. The Board of Commissioners hereby approves and authorizes the Chairman
PDF

[Adopted this 24th day of October, 2023.]
Adopted this 24th day of October, 2023.
PDF

[Exhibit A]
Exhibit A
PDF

[of the Board of Commissioners, hereby acknowledges and agrees that based on the TEFRA]
of the Board of Commissioners, hereby acknowledges and agrees that based on the TEFRA
PDF

[This 24th day of October, 2023.]
This 24th day of October, 2023.
PDF

[CLERK’S CERTIFICATE]
CLERK’S CERTIFICATE
PDF

[SGMC Re: Proposed Reissuance of the Revenue Anticipation Certificate Financing by the Hospital Authority of Valdosta and Lowndes County, Georgia]
SGMC Re: Proposed Reissuance of the Revenue Anticipation Certificate Financing by the Hospital Authority of Valdosta and Lowndes County, Georgia
PDF

[Very truly yours, Michele Madison, Hearing Officer of the Hospital Authority of Valdosta and Lowndes County, Georgia]
Very truly yours, Michele Madison, Hearing Officer of the Hospital Authority of Valdosta and Lowndes County, Georgia
PDF

[TEFRA HEARING CERTIFICATE]
TEFRA HEARING CERTIFICATE
PDF

[GIVEN under my hand, this 16th day of October, 2023. Michele Madison TEFRA Hearing Officer]
GIVEN under my hand, this 16th day of October, 2023. Michele Madison TEFRA Hearing Officer
PDF

[NOTICE OF PUBLIC HEARING on the 12th day of October, 2023 at 2:00 p.m.]
NOTICE OF PUBLIC HEARING on the 12th day of October, 2023 at 2:00 p.m.
PDF

[By: /s/ Hearing Officer]
By: /s/ Hearing Officer
PDF

October-9-2023-Work-Session-Minutes

[Page 1]
Page 1
PDF

October-10-2023-Regular-Session-Minutes

[Page 1]
Page 1
PDF