Packet: Missing ULDC Text Amendment, new well, force main, and elevator with For Consideration and Bids from previous cancelled session @ LCC 2024-02-26 [Up]
LAKE blog post:
Documents received in response to a LAKE open records request:
Packet: new well, force main, and elevator @ LCC 2024-02-26
For Consideration
PDF
BUDGET IMPACT: $47,884.00; During Hurricane Idalia, the Clyattville tower was destroyed. This tower provided all connectivity for the Clyattville Fire Department, to include telephony, computer network connections, and video.
PDF
02272024Plus-0004 BUDGET IMPACT: $274,765.00; Staff has negotiated the purchase of the Right of Way (ROW) for Parcels 1-2, 6A-43 for the Kinderlou-Clyattville Road TSPLOST project.
PDF
BUDGET IMPACT: $-1,115,000.00; the TIA office has agreed to provide additional funds of $1,115,000.00 to cover the total cost of the project.
PDF
BUDGET IMPACT: N/A; Quarterman Estates Subdivision Phase 4, Section 2 is located in the southern portion of Lowndes County, off of White Water Road and includes 33 lots.
PDF
BUDGET IMPACT: $71,500.00 Spring Creek well has high organic levels in the water being pumped from the aquifer that creates disinfection byproducts when the water is chlorinated... causing elevated trihalomethanes and haloacidic acids... RFP for a pilot study ... feasibility of installing a water treatment plant ... Harn RO ... three-month pilot is $62,650.00, an extra month can be added if needed for an additional $8,850.00.
PDF
BUDGET IMPACT: $91,980.00 The elevator is broken down ... built in the late 80's and parts are no longer available ... three bids that met specifications.
PDF
BUDGET IMPACT: $9,613.50; Lowndes County solicited bids to repair damaged buildings at the 4-H Camp due to Hurricane Idalia. FEMA will be reimbursing Lowndes County for approximately 87% of the repairs.
PDF
BUDGET IMPACT: $2,584.92; Lowndes County solicited bids to repair damaged portions of the Lowndes County Governmental Building, due to Hurricane Idalia. FEMA will be reimbursing Lowndes County for approximately 87% of the repairs.
PDF
BUDGET IMPACT: $100,572.45 Golden Oaks Subdivision ... adjacent to Val-Tech lift station on Shiloh Road. This neighborhood is over thirty years old, and the septic systems are beginning to fail... several calls from residents over the last year desiring to connect to our system. Staff ... determined that installing an E/One Force Main is a viable option... bids were received from James Warren & Associates for $100,572.45, and RPI, Inc. for $108,936.30.
PDF